Ruwais Refinery West Plant Restoration Project- Demolition Works

Ruwais Refinery West Plant Restoration Project- Demolition Works

Project Overview:

The scope includes the following Demolition Works in RRW Plant Units-

  • 1220-Whole Cracked Naphtha Hydrotreater unit & 1630-Propylene Recovery Unit.
  • Demolition of Steel Structures – 2,921 MT
  • Demolition of Equipment’s – 2,735 MT
  • Cold Cutting & Demolition of Piping – 53,137 LM
  • Demolition of Electrical & Instrumentation items
  • Civil Demolition Works – Excavation/Disposal = 122,000 M3
  • Concrete Demolition = 6,256 M3, Asphalt Demolition = 600 M3

 

Gallery:

 

Project details
  • 06 months
  • US$ 23,679,806
  • Ruwais, Abu Dhabi
  • TAKREER
  • GS Engineering and Construction
  • P.O. Box 47467, Mussafah Industrial Area, Abu Dhabi,UAE
  • +971 2 554 6550
  • d@ajes.ae
  • Sun – Thu 07:30 – 17:30