Fujairah Water Transmission System Project Phase 1

Project Overview:

(Joint Venture with Technip)

Major work scope’s included 64″ Carbon Steel Pipelines (Twin lines) – 185  Kms. each. 24″ Carbon Steel Pipelines (Twin lines) – 18 Kms. Each. Steel Tanks of 130 MIGD Capacities & One Pumping Station.

 

Gallery:

 

Project details
  • 24 months
  • US$ 301,765,406
  • Taweelah to Fujairah,Abu Dhabi
  • U.A.E. Offsets Group
  • Technip
  • P.O. Box 47467, Mussafah Industrial Area, Abu Dhabi,UAE
  • +971 2 554 6550
  • d@ajes.ae
  • Sun – Thu 07:30 – 17:30