Borouge 2 Project – Off sites & Utilities

Borouge 2 Project – Off sites & Utilities

Project Overview:

Subcontract for Civil Works & Effluent Treatment Plant Project

Civil works subcontract scope included demolition works, site preparation, excavation, back filling, concrete works, paving and roads, fire proofing and  underground piping (HDPE, MDPE), etc.

ETP Plant work scope was an EPC contract (Consortium with METITO) for the design, supply of all materials and equipment, construction and commissioning of an Effluent Treatment Plant for the Borouge 2 expansion.

 

Gallery:

 

Project details
  • 35 months
  • US$ 113,018,216 (Civil Works), US$ 31,749,984 (ETP)
  • Ruwais, Abu Dhabi
  • BOROUGE
  • Technicas Reundias
  • P.O. Box 47467, Mussafah Industrial Area, Abu Dhabi,UAE
  • +971 2 554 6550
  • d@ajes.ae